Green Technology Metals’ Seymour gets environmental green light

Green Technology Metals (ASX:GT1) has received formal notification confirming completion of the environmental assessment (EA) process for its Seymour Lithium Project in northwestern Ontario, Canada.

The Ontario Ministry of Natural Resources (MNR) issued a statement of completion for the permit to remove forest resources. GT1 says this ‘major’ milestone allows government agencies to issue development permits across the applied project area.

The company submitted its project description in November 2022 and received a Category B classification from the ministry in September 2023.

According to GT1, this designation reflects potential low to medium environmental impacts, which aligns with Seymour’s processing model that uses gravity-based separation and no chemicals to produce concentrate.

Managing Director Cameron Henry says the EA completion is ‘extremely pleasing’, noting that it highlights the ‘low-risk’ profile of the development.

“The project is a simple small- to medium-sized operation that is extremely environmentally friendly given that we simply extract the raw minerals, sort and wash them, and then use gravity to separate the unwanted material from the spodumene we are concentrating,” Henry says.

“Although larger in scale, the process and operation are not too dissimilar from a quarrying operation that is used for sourcing of road base materials and uses techniques and processing that are well known in the industry.

“The receipt of the EA is another milestone completion on our pathway to permitting the Seymour mine and highlights the ongoing work progressed by our team throughout the lithium market downturn and continuing into this next cycle for the commodity we’re currently in.”

Read the full article by mining.com.au | https://mining.com.au/green-technology-metals-seymour-gets-environmental-green-light/

Scroll to Top

Work Scope/Contract No 2 - Site access road maintenance includes

  • regular inspections and repairs of the Jack Fish road turn off to Seymour to ensure safe and reliable access for vehicles and equipment
  • upkeep of the Armstrong Accommodation Camp access and internal roads
  • grading, resurfacing, snow removal, and drainage management to prevent erosion and maintain road integrity
  • implementing safety and environmental compliance measures, scheduling routine maintenance, and providing progress reports to stakeholders

 The goal is to maintain optimal road conditions, minimize downtime, and ensure compliance with safety and environmental standards

 Procurement Strategy: Daily rate plus materials

Location: Seymour Mine Site

Equipment: Grader, water cart, drum compactor, snow plough, wheel loader, tipper truck, road sweeper

Likely team size: 2-4 staff on 2 x 2 roster (12-hour day shift)

Duration: 3 years minimum

Work Scope/Contract No 1 - Surface Crushing Plant and Operation for Seymour Mine construction

  • site preparation, supply and installation of crushing and screening equipment
  • establishing operational procedures for material handling and crushing operations to crush excavated waste rock to the appropriate sizes and specifications to serve as construction gravel
  • implementing safety and environmental compliance measures, scheduling regular maintenance, and monitoring systems to ensure optimal performance

The goal is to produce high-quality aggregate materials efficiently while adhering to safety, environmental, and quality standards, and providing regular progress reports to stakeholders

Procurement Strategy: Supply, Install and Operate

Location: Seymour Mine Site

Equipment: Surface Crushing Plant and Loader

Likely team size: 2-3 staff on 2 x 2 roster (12-hour day shift)

Duration: 12 months

Power Supply: by GT1

Feed rock hardness and size: TBA

Final screened product sizes: TBA