COARSE SPODUMENE CONCENTRATE PRODUCED AT SEYMOUR WITH LITHIUM RECOVERY EXCEEDING 72%



Highlights

  • Flagship Seymour concentrate recovery exceeds 72% using heavy liquid separation ▪ Confirms simple 2 stage DMS flowsheet potential

  • Critical milestone for the PEA and future off-take partners

  • Test work based on 1000kg of representative composites as per preliminary mine plan

  • Very high recovery due to large spodumene crystal size

  • Concentrates now being sent for conversion work to Lithium Hydroxide


Green Technology Metals Limited (ASX: GT1) (GT1 or the Company), a Canadian-focused multi-asset lithium business, is pleased to announce very high spodumene concentrate recoveries from its 100%-owned Seymour Project, located approximately 250km north of Thunder Bay in Ontario, Canada. The spodumene concentrate represents a critical milestone for the business and future off-take partners.


Figure 1: DMS test work being undertaken at SGS Canada’s facilities in Lakefield, Ontario


“The next few months will be an exciting time for the team at GT1 as we focus on increasing the value of our Flagship Seymour Project through metallurgical test work. These results will culminate part of our Preliminary Economic Assessment (PEA) and marks another important step closer to building a vertically integrated lithium business in Ontario, Canada.”


- GT1 Chief Executive Officer, Luke Cox





Green-Technology-Metals-Black.png

CANADA

AUSTRALIA

+1 807 621 0854

Thunder Bay
160 Logan Avenue, Thunder Bay, Ontario P7A 6R1


Toronto

241 Yonge St,

Toronto,

Ontario M5B 1N8

+61 8 6557 6825

Perth
Level 1, 338 Barker Road

Subiaco WA 6008 Australia

b61c7e_e9e5992a0dd84feca144515f9dab5877_mv2.png

SUBSCRIBE

Sign up to receive Green Technology Metals news and updates.

bottom of page